Rowley Hall Renovation

Timeline

    JANUARY

  • Demolish interior sections of building undergoing renovation

    FEBRUARY

  • Install plumbing
  • Perform electrical work in the walls
  • Install walls

    MARCH

  • Complete HVAC, electrical, plumbing, and sprinkler work in the ceilings

    APRIL

  • Install ceilings
  • Begin exterior window installation and restoration

    MAY/JUNE

  • Install architectural finishes for the interiors, exterior windows and restoration

    JULY

  • Install furnishings

    AUGUST

  • Move-in of office personnel and resident students
  • Project completion